All projects
MEP2024Huiyang, HuizhouYB-MEP-2024-012
Battery plant HVAC systems
Temperature and humidity control for battery production areas, plus office VRV and smoke exhaust.
Project facts
Gross floor area
60,000 m²
Contract duration
150 days
Actual duration
138 days
Completion
2024
Scope split
Construction10%
MEP90%
Construction timeline
2023.10
Load calculation
Plant-wide heating, humidity and cooling loads calculated
2023.12
Procurement
Chillers and terminal units ordered
2024.03
Installation
Piping, ductwork and equipment installed
2024.06
Commissioning
Full-system integrated test and performance acceptance
Location in Guangdong
GuangzhouDongguanFoshanShenzhen
Huiyang, Huizhou
Have a similar project?
Send drawings, a bill of quantities or just a site address. We reply within one business day with an indicative scope, schedule and budget range.