MEP2024Liaobu, DongguanYB-MEP-2024-005
Food plant clean-air and HVAC
Three-stage filtration with temperature and humidity control for a food plant, accepted to GMP requirements.
Project facts
Gross floor area
12,000 m²
Contract duration
60 days
Actual duration
55 days
Completion
2024
Scope split
Construction5%
MEP95%
Construction timeline
2023.12
Design development
Cleanliness class and temperature/humidity scheme fixed
2024.01
Equipment delivery
Air-handling and filtration units on site
2024.02
Installation
Ductwork, piping and controls installed
2024.03
GMP acceptance
Cleanliness and temperature/humidity both passed