MEP2024Liaobu, DongguanYB-MEP-2024-005

Food plant clean-air and HVAC

Three-stage filtration with temperature and humidity control for a food plant, accepted to GMP requirements.

Food plant clean-air and HVAC — schematic illustration

Project facts

Gross floor area
12,000 m²
Contract duration
60 days
Actual duration
55 days
Completion
2024

Scope split

Construction5%
MEP95%

Construction timeline

2023.12
Design development

Cleanliness class and temperature/humidity scheme fixed

2024.01
Equipment delivery

Air-handling and filtration units on site

2024.02
Installation

Ductwork, piping and controls installed

2024.03
GMP acceptance

Cleanliness and temperature/humidity both passed

Location in Guangdong

GuangzhouDongguanFoshanShenzhen

Liaobu, Dongguan