MEP2024Nanhai, FoshanYB-MEP-2024-003

Electronics cleanroom — ISO 7

ISO 7 cleanroom with FFU units, air-handling units and air showers for an electronics plant.

Electronics cleanroom — ISO 7 — schematic illustration

Project facts

Gross floor area
8,500 m²
Contract duration
75 days
Actual duration
68 days
Completion
2024

Scope split

Construction5%
MEP95%

Construction timeline

2024.01
Envelope

Sandwich panel partitions and ceiling complete

2024.02
Equipment

FFU and air-handling units installed

2024.03
Pipework

Ductwork and refrigerant piping installed

2024.04
Cleanroom acceptance

Particle counts passed; GMP acceptance