MEP2024Nanhai, FoshanYB-MEP-2024-003
Electronics cleanroom — ISO 7
ISO 7 cleanroom with FFU units, air-handling units and air showers for an electronics plant.
Project facts
Gross floor area
8,500 m²
Contract duration
75 days
Actual duration
68 days
Completion
2024
Scope split
Construction5%
MEP95%
Construction timeline
2024.01
Envelope
Sandwich panel partitions and ceiling complete
2024.02
Equipment
FFU and air-handling units installed
2024.03
Pipework
Ductwork and refrigerant piping installed
2024.04
Cleanroom acceptance
Particle counts passed; GMP acceptance