New energy2023Shunde, FoshanYB-PV-2023-002

Shunde logistics park rooftop PV

Distributed rooftop photovoltaic plant with self-consumption and surplus export to the grid.

Shunde logistics park rooftop PV — schematic illustration

Project facts

Gross floor area
45,000 m² (roof area)
Contract duration
120 days
Actual duration
105 days
Completion
2023

Scope split

Construction10%
MEP90%

Construction timeline

2023.05
Mounting

Roof mounting rails installed

2023.07
Modules

PV modules installed and wired

2023.08
Grid connection

Connected and generating

Location in Guangdong

GuangzhouDongguanFoshanShenzhen

Shunde, Foshan