Tianhe commercial complex — phase 2

Mixed retail, office and leisure complex delivered in two phases.

Tianhe commercial complex — phase 2 — schematic illustration

Project facts

Gross floor area
120,000 m²
Contract duration
360 days
Actual duration
345 days
Concrete volume
45,000 m³
Steel tonnage
1,200 t
Completion
2022

Scope split

Construction45%
MEP35%
Fit-out20%

Construction timeline

2021.10
Substructure

Basement structure complete

2022.04
Superstructure

Tower topped out

2022.08
Facade

Curtain wall installed

2022.10
Handover

Opened to the public